Goodwood Blvd Sidewalks & Bike Path Project

Project Description: The project includes approximately 1.3 miles of new sidewalks on both sides of Goodwood Boulevard from Airline Highway to Sharp Road, bike lane restriping, upgraded signage, pavement markings, and new crosswalk striping at Broadmoor Elementary School and Broadmoor High School. Together, these improvements are designed to make the corridor safer and more accessible. They will support people walking, biking, driving, and traveling near area schools.

Council District: 6

Project Type: Call For Projects

Current Phase: Construction

Design Consultant: Sustainable Design Solutions

Project Manager: Nick Prudhomme

Contractor: Procivil Construction, LLC

Current Cost Estimate ($M): $2.00

Estimated Advertisement Date: May 2026

Project Updates

Date Status
09/2026 Bids were opened and contract was awarded. Groundbreaking held Sept. 30. Construction underway.
05/2026 Final plans received. Targeting May '26 Construction Advertisement.
04/2026 Final plans submitted. Bod Docs being prepared.
01/2026 Final Plans submitted and coordinating final details with adjacent projects in this area.
12/2025 90% Plan Review complete. Comments returned and pickups ongoing.
11/2025 90% Plans submitted and under PMT review.
10/2025 The Design Consultant is now preparing 90% Final Plans.
04/2025 The Design Consultant is currently preparing 60% Final Plans.
09/2024 The Design Consultant is under contract and topographic survey and design study is underway.
08/2023 This project is in the planning phase based on prioritization. No design activity is underway.