Q4 2025 Progress Report

The following information is accurate through December 31, 2025.

PROJECT PHASE
Phases Current Report
PLANNING 21
DESIGN 38
RIGHT OF WAY/UTILITIES 8
CONSTRUCTION 23
CONSTRUCTION COMPLETE 47
TOTAL PROJECTS 137

Note: 72 projects were included in the original MOVEBR proposition. A number of these projects, such as ADA improvements and signalization, have been separated into specific, standalone projects for design and construction. The total number of projects listed reflects all of these and will continue to increase in the future, but will always align with the original 72 projects approved for the MOVEBR program.

 

DOLLARS SPENT

(Cumulative including Administrative Fees)

SOURCE Current Report ($)
MOVEBR $220,269,995
GLP $56,342,438
OTHER $73,491,246
TOTAL $350,103,679
LOCAL & SMALL BUSINESS DOLLARS COMMITTED

(Cumulative - Does not include contracts under negotiation)

Category Type Current Report ($) (%)
Local Parish Companies $260,465,279 73.49%
Local State Companies $84,372,157 23.80%
Small Business Minority Owned Businesses $58,476,562 16.50%
Small Business Woman Owned Businesses $25,133,184 7.09%
Small Business Veteran Owned Businesses $3,144,883 0.89%
Small Business Total $86,754,629 24.48%
Small Business Target   20%

 

CURRENT STAGE
Key Benefit Planned Planning Design Construction Construction Completed
Lane Miles of New Roadway 99.08 35.7% 37.2% 23.8% 3.3%
Lane Miles of Enhanced Roadway 115.43 24.2% 30.0% 43.5% 2.3%
Miles of Sidewalk 260.16 9.3% 70.7% 13.9% 6.1%
Miles of Bike Paths 65.32 21.1% 38.3% 38.3% 2.3%
Signals Upgraded 96 24.0% 52.1% 20.8% 3.1%
Signals Replaced 90 4.4% 4.4% 91.1% 0.0%
Miles of Fiber for Signals 177.16 0.0% 0.6% 0.1% 99.3%
New School Flashers 302 0.0% 1.7% 1.0% 97.4%

Planned value is updated per project based upon the current planned amount per key benefit. Percentages by phase are calculated based upon the summation of all projects in the MOVEBR and their appropriate Project Phase. Design includes Engineering Procurement, Design, ROW, and Utilities. Construction includes Construction Procurement and Construction. Completed indicates Project Acceptance has been reached.

 

Communication/Outreach

PUBLIC CONTACT
Item Current Report
No. of Public Contacts Received* 2,311
Required Responses to Public Inquiries 2,165

*Questions/inquiries through website, social media, email, calls, etc. Numbers are cumulative since the program's inception.

 

Procurement

EXECUTED CONTRACTS BY MONTH
Month Number of Contracts Executed
January 2025 8
February 2025 2
March 2025 18
April 2025 7
May 2025 9
June 2025 17
July 2025 1
August 2025 3
September 2025 15
October 2025 9
November 2025 5
December 2025 1

Contracts executed through the Office of the Mayor-President.

 