Centurion Ave. Sidewalks (O'Neal Ln to Crossbow Dr.) Project Page

Project Description: This project is on a suburban local road that connects to the O’Neal Lane corridor. This project will enhance pedestrian mobility by connecting existing sidewalk at O’Neal Lane on both sides of Centurion Ave. to Crossbow Dr. This segment of roadway is the entrance to a residential subdivision.

Council District: 9

Project Type: Community Enhancement

Current Phase: Construction Complete

Design Consultant: WTAA Engineers

Project Manager: Henok Abebe

Proposition Budget: $200,000

Estimated Letting Date: July 2021

Project Updates

Date Status
12/2022 Construction is complete.
05/2022 Construction is underway.
12/2021 Notice to Proceed set for January 10,2022.
09/2021 Bid opening 7-27-21. Construction planned to begin late October 2021.
05/2021 The Design Consultant is preparing the 100% plan submittal.
02/2021 The Design Consultant is preparing the 90% final plan submittal.
01/2021 The Design Consultant has submitted the preliminary plan submittal and is currently under review by the Program Management Team and Department of Transportation and Drainage.

Documents

Photos

Construction Components

Contractor Contract Description Contract Value Estimated Completion Date
The Luster Group, LLC Construction Services $88,554.00 Q2 2022

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.