Highland at Pecue Project Page

Project Description: This project proposes to improve the existing intersection conditions for Highland Rd. at Pecue Ln. by converting the current three-leg intersection into a roundabout intersection. The project will also consider safety and traffic calming improvements for each approaching leg to the new intersection.

Council District: 3, 9

Project Type: Corridor Improvements

Current Phase: Engineering Procurement

Design Consultant: T. Baker Smith, LLC

Project Manager: Mary Frances O'Rourke

Proposition Budget: $3,000,000

Estimated Letting Date: 2026

Project Updates

Date Status
11/2023 Project is currently in the procurement phase for design services.
08/2023 This project is advertised for the selection of an Engineering Design Consultant.
05/2022 This project is in the planning phase based on prioritization. No design activity is underway.

 