Highland at Pecue Project Page

Project Description: This project proposes to improve the existing intersection conditions for Highland Rd. at Pecue Ln. by converting the current three-leg intersection into a roundabout intersection. The project will also consider safety and traffic calming improvements for each approaching leg to the new intersection.

Council District: 3, 9

Project Type: Improve Existing Corridors

Current Phase: Design

Design Consultant: T. Baker Smith

Project Manager: Mary Frances O'Rourke

Proposition Budget: $3,000,000

Estimated Letting Date: Q3 2025

Project Updates

Date Status
10/2024 Design Consultant is finalizing topographic survey and the design study.
09/2024 Design Consultant is performing topographic survey and working on design study.
08/2024 This project is currently in the Design Study Phase.
11/2023 Project is currently in the procurement phase for design services.
08/2023 This project is advertised for the selection of an Engineering Design Consultant.
05/2022 This project is in the planning phase based on prioritization. No design activity is underway.

 