Lee Dr (Highland Road - Perkins Road) Project Page

Project Description: The scope of work includes capacity and turning movements. Lee Drive is a five-lane section from the intersection with Highland Road for 400 feet and then is a two-lane roadway to Perkins Road. A bridge crosses just south of Liberty High School. From the school to Perkins, Lee Drive is a residential corridor. The project will include capacity improvements as well as complete streets components for pedestrians and bicyclists.

Council District: 12

Project Type: New Capacity

Current Phase: Design

Design Consultant: Aracadis

Project Manager: Kate Prejean

Proposition Budget: $35,000,000

Estimated Letting Date: Q3 2025

Project Updates

Date Status
09/2024 60% final design plans are complete. The right-of-way acquisition process is scheduled to begin Quarter 4 of 2024, generally within the segment between Highland Road and the bridge first. Upon completion of all acquisition, the utility companies will begin relocations.
08/2024 60% final design plans are complete. The right-of-way acquisition process is scheduled to begin Quarter 3 of 2024, generally within the segment between Highland Road and the bridge first. Upon completion of all acquisition, the utility companies will begin relocations.
05/2024 Final plans are in progress. The right-of-way acquisition process is scheduled to begin Quarter 2 of 2024, generally within the segment between Highland Road and the bridge first. Upon completion of all acquisition, the utility companies will begin relocations.
01/2024 Final plans are in progress. The right-of-way acquisition process is scheduled to begin Quarter 1 of 2024, generally within the segment between Highland Road and the bridge first. Upon completion of all acquisition, the utility companies will begin relocations.
09/2023 Final plans are in progress. The right-of-way acquisition process is scheduled to quarter 4 of 2023 generally within the segment between Highland Road and the bridge first. Upon completion of all acquisition, the utility companies will begin relocations.
07/2023 Final plans are in progress. The Right of Way acquisition process is scheduled to begin Fall 2023.
01/2023 Final plans are in progress. The right-of-way acquisition process will begin in Quarter 1 of 2023. Utility relocations will follow acquisition of right of way.
06/2022 This project is currently in final design.
03/2021 The Consultant is continuing surveying, traffic, and Design Study activities.
02/2021 The Consultant has begun surveying activities and the Design Study. 
11/2020 Contracting is underway with the Engineering Design Consultant to begin development of final plans.

 

Documents

Videos

Watch drone footage of Lee Drive

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.