Midway (Constantin - Picardy) Project Page

Project Description: Construction of a new two-lane road from Picardy Avenue to Constantin Phase 2 (also a MOVEBR project), including pedestrian and bicycle facilities and sewer work.

Council District: 11

Project Type: New Capacity

Current Phase: Construction

Design Consultant: Stantec

Project Manager: Brian Smith

Proposition Budget: $6,500,000

Estimated Letting Date: October 2021

Project Updates

Date Status
12/2024 Construction is nearing completion. Construction of roadway lighting and roadway striping is planned through December 2024. Final completion is expected in January 2025.
10/2024 Construction is nearing completion. Construction of roadway lighting and roadway striping is planned through December 2024.
09/2024 Construction is nearing completion. Closures are underway to construction the intersections. Construction is planned through October 2024.
08/2024 The contractor is preparing the roadway corridor for construction of the Midway Dr. pavement. Construction of Asphalt roadway and Picardy intersection work to begin the first week of September. Construction is planned through October 2024.
06/2024 The contractor is preparing the roadway corridor for construction of the Midway Dr. pavement. Construction is planned through October 2024.
05/2024 The contractor is preparing the roadway corridor for construction of the Midway Dr. pavement. Construction is planned through September 2024.
01/2024 The contractor is preparing the roadway corridor for construction of the Midway Dr. pavement. Construction is planned through May 2024.
09/2023 The contractor is preparing the roadway corridor for construction of the Midway Dr. pavement. Construction is planned through the beginning of 2024.
07/2023 The contractor is preparing the roadway corridor for construction of the Midway Dr. pavement. Construction is planned through the end of 2023.
01/2023 The contractor is installing the subsurface drainage and sewer lines for the Midway Dr. project. Construction is planned through the middle of 2023.
03/2022 The contractor has begun mobilizing for the construction of the Midway Dr. project.
11/2021 The Midway Rd project is currently being advertised for construction.
10/2021 The Design Consultant is finalizing Construction Plans for project letting before the end of the year.
08/2021 The Design Consultant is finalizing the construction drawings and the Final plans will be completed by the end of the year.
05/2021 The Design Consultant is developing the design plans. Final plans will be completed by the end of the year.
10/2020 The Design Consultant is preparing the 60% (plan in hand) design submittal.

 

Documents

Videos

Watch the Virtual Public Meeting Held on October 12, 2021

Construction Components

Contractor Contract Description Contract Value Estimated Completion Date
Boone Services Construction Services $4,359,386.03

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.