| Date |
Status |
| 03/2026 |
The award of the construction project for Phase A (Flannery bridge) is complete and the construction contract is being executed. Phase B, which includes the construction of the roundabout at S. Flannery, will follow Phase A and utility relocations that are ongoing. |
| 02/2026 |
The award of the construction project for Phase A (Flannery bridge) is still under review and pending. Phase B, which includes the construction of the roundabout at S. Flannery, will follow Phase A and utility relocations that are ongoing. |
| 12/2025 |
The award of the construction project for Phase A (Flannery bridge) is pending. The award will be followed by an assembly period for the contractor and a notice to proceed by the end of the year. Phase B, which includes the construction of the roundabout at S. Flannery, will follow Phase A and utility relocations that are ongoing. |
| 07/2025 |
The award of the construction project for Phase A (Flannery bridge) is pending. |
| 03/2025 |
The project will be re-advertised for construction in Q2 of 2025 for Phase A, South Flannery Bridge. Clearing and utility relocations are still on-going along Old Hammond Highway for Phase B construction. |
| 12/2024 |
The LADOTD has issued a permit for the construction of the OHH Seg 1 Phase A project. The project was advertised and bids were received in November 2024. The bids are being reviewed by the City-Parish. Clearing and utility relocations have begun along Old Hammond Highway for Phase B construction. |
| 09/2024 |
The LADOTD has issued a permit for the construction of the OHH Seg 1 Phase A project. The project will be advertised in October with construction expected to begin in the field just prior to the first of th year. Clearing and utility relocations have begun along Old Hammond Highway for Phase B construction. |
| 08/2024 |
Phase A, is pending a approval for construction from LA DOTD. The project advertisement was pulled prior to the bid date and will be readvertised after the permit is received. Clearing and utility relocations have begun along Old Hammond Highway for Phase B construction. |
| 05/2024 |
Phase A, S. Flannery Road Bridge, will be readvertised for construction in June 2024. Right-of-way acquisition has been completed for Phase B. Clearing and utility relocations have begun along Old Hammond Highway for Phase B construction. |
| 03/2024 |
Phase A, S. Flannery Road Bridge, will let for construction in 3/2024. Right-of-way acquisition has been completed for Phase B. Clearing and utility relocations have begun along Old Hammond Highway for Phase B construction. |
| 01/2024 |
Phase A, S. Flannery Road Bridge, was advertised for construction in August 2023, but a contractor was not awarded the project. Project will be readvertised in 2024. Right-of-way acquisition has been completed for Phase B. Clearing and utility relocations have begun along Old Hammond Highway for Phase B construction. |
| 11/2023 |
Phase A, S. Flannery Road Bridge, was advertised for construction in August 2023, but a contractor was not awarded the project. Project will be readvertised in 2024. Currently, right-of-way acquisition is still underway for Phase B. Phase B will be constructed after Phase A and will include the roundabout at Old Hammond and S. Flannery and the roadway from the roundabout to Millerville. |
| 09/2023 |
Phase A consists of the reconstruction of S. Flannery to Goodwood including the replacement of the bridge. All right-of-way acquisition for Phase A has been completed. Currently, acquisition is still underway for Phase B. Phase A was advertised for construction in August 2023. Phase B will be constructed after Phase A and will include the roundabout at Old Hammond and S. Flannery and the roadway from the roundabout to Millerville. |
| 07/2023 |
"The design of Phase A is complete. Phase A will consist of the reconstruction of S. Flannery to Goodwood. Phase A will be advertised for construction in August 2023 and let in September. Construction will begin in the end of 2023 and is expected to take less than 1 year. During a portion of the construction time, Flannery will be closed for the reconstruction of the bridge. More information will be provided as dates for closures are set.
Right-of-way acquisition is underway for Phase B based on the final design plans that are being finalized. Phase B will be constructed after Phase A and will include the roundabout at Old Hammond and S. Flannery and the roadway from the roundabout to Millerville. " |
| 01/2023 |
Design engineer has completed final construction plans for Phase A. Phase A will consist of the reconstruction of S. Flannery to Goodwood. Currently, right of way acquisitions are underway for the entire project. Once the required right of way has been acquired, Phase A will be advertised for construction in early 2023. Phase B will be constructed after Phase A and will include the roundabout at Old Hammond and S. Flannery. |
| 06/2022 |
The Design Engineer is preparing the final construction plans and documents for the first phase of construction. Right of way acquisition is on-going. Wetlands permit documents have been submitted. |
| 08/2021 |
The consultant is preparing the construction plans and documents. |
| 05/2021 |
The Design Consultant is developing design plans for the corridor. |
| 02/2021 |
The Design Consultant is revising the 30% final plan submittal. A public meeting will be held late Q1/early Q2 to present the design of this project. |
| 10/2020 |
The Design Consultant is preparing the 30% final plan submittal. |