Constantin (Midway - Bluebonnet) Project Page

Project Description: Construction of a new 4-lane phase of Constantin/Dijon from the end of phase 1 that passes alongside the Children's Hospital, with an intersection at the new MOVEBR Midway project and on to Bluebonnet through the health district and along I-10.

Council District: 11

Project Type: New Capacity

Current Phase: Construction

Design Consultant: Stantec

Project Manager: Brian Smith

Proposition Budget: $8,000,000

Estimated Letting Date: May 2023

Project Updates

Date Status
01/2024 Construction in the field started in December 2023 and is expected to continue through Q3 of 2025. The contractor, Boone Services, is clearing the corridor and placing the embankment for the future roadway.
12/2023 Boone Services was awarded the construction contract for Constantin. Construction in the field started in December 2023 and is expected to continue through Q3 of 2025.
09/2023 Boone Services was awarded the construction contract for Constantin. The work is expected to start in the field in Q4 of 2023.
07/2023 The project was let for construction in mid-June by the LA DOTD. The construction is expected to begin in September 2023.
01/2023 The Design Consultant is finalizing the construction drawings. Project advertisement is scheduled for February 2023.
06/2022 The Design Consultant is finalizing the construction drawings for submittal to MOVEBR. Project letting is scheduled for December 2022.
09/2021 The Design Consultant is finalizing the construction drawings for submittal to MOVEBR.
08/2021 The Design Consultant is finalizing the ROW and construction drawings for submittal to MOVEBR.
06/2021 The intersection alignment at Bluebonnet is being revised by the Design Consultant while finalizing the construction drawings.
05/2021 The intersection alignment at Bluebonnet is being revised by the Design Consultant while finalizing the plan package.
02/2021 The revised alignment will be developed as soon as the revised environmental document is approved by FHWA.
10/2020 Negotiations and contracting are underway with the Engineering Design Consultant to begin development of final plans and update to the environmental process.

 

Documents

Photos

Videos

Watch the Virtual Public Meeting Held on October 12, 2021

Construction Components

Contractor Contract Description Contract Value Estimated Completion Date
Brown Industrial Construction, LLC Construction Services $7,828,509.40

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.