Constantin (Dijon Midway - Bluebonnet) Project Page

Project Description: Construction of a new 4-lane phase of Constantin/Dijon from Midway to Bluebonnet through the health district and along I-10. Alternative alignment is being pursued to avoid the create a better intersection with Bluebonnet. The DOTD will administer the construction phase.

Council District: 11

Project Type: New Capacity

Current Phase: Engineering Procurement

Design Consultant: Stantec

Project Manager: Brian Smith

Proposition Budget: $8,000,000

Estimated Letting Date: 2022

Project Updates

Date Status
02/2021 The revised alignment will be developed as soon as the revised environmental document is approved by FHWA.
10/2020 Negotiations and contracting are underway with the Engineering Design Consultant to begin development of final plans and update to the environmental process.

 

Documents

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.