Constantin (Dijon Midway - Bluebonnet) Project Page

Project Description: Construction of a new 4-lane phase of Constantin/Dijon from Midway to Bluebonnet through the health district and along I-10. Alternative alignment is being pursued to avoid the create a better intersection with Bluebonnet. The DOTD will administer the construction phase.

Council District: 11

Project Type: New Capacity

Current Phase: Design

Design Consultant: Stantec

Project Manager: Brian Smith

Proposition Budget: $8,000,000

Estimated Letting Date: Q2 2022

Project Updates

Date Status
09/2021 The Design Consultant is finalizing the construction drawings for submittal to MOVEBR.
08/2021 The Design Consultant is finalizing the ROW and construction drawings for submittal to MOVEBR.
06/2021 The intersection alignment at Bluebonnet is being revised by the Design Consultant while finalizing the construction drawings.
05/2021 The intersection alignment at Bluebonnet is being revised by the Design Consultant while finalizing the plan package.
02/2021 The revised alignment will be developed as soon as the revised environmental document is approved by FHWA.
10/2020 Negotiations and contracting are underway with the Engineering Design Consultant to begin development of final plans and update to the environmental process.

 

Documents

Comments